CENTRAL GOVERNMENT EMPLOYEES WELFARE HOUSING
ORGANISATION
(Under M/O Housing and Urban Poverty Alleviation )
Hindi Website Beneficiary Feedback

Project Completed

Particular

Land area (acres)

Scheme announcement

Commencement of const.

Completion of construction

No. of DUs constructed

Approx. escalation

Final average cost/sq ft (Rs)

Total cost of project (Rs in Crore)

Remarks

Project Gallery

Ahmedabad

6.41

Mar 99

Feb 02

Oct 05

310

16.5%

630

18

Handed Over

Click Here to View Gallery

Aimt (Ph-I)

15

-

Aug 03

Mar 05

-

-

-

20

Handed Over

-

Aimt (Ph-II)

15

-

Nov 05

Mar 07

-

-

-

11

Handed Over

-

Bangalore

8.2

July'97

Aug'98

Mar 01

603

0.44%

700

45

Handed Over

Click Here to View Gallery

Bhubneshwar (Ph-I)

5.0

Dec 06

Oct 08

Jan 13

256

30%

1641

55

Handing Over in Progress. 245DUs already handed over

Click Here to View Gallery

Chandigarh

10

July'96

Dec'97

May 00

305

1.80%

707

25.92

Handed Over

Click Here to View Gallery

Chennai (Ph-I)

10

Dec 92

Mar 94

Oct 95

524

Nil

442

19

Handed Over

-

Chennai (Ph-II)

11.32

Nov 05

Aug 07

Feb 12*

572

30%

1352

71

Handing Over in Progress. 558 DUs already handed over

Click Here to View Gallery

Gurgaon (Ph-I)

25

July'95

April'97

July 99

1088

3.50%

680

65

Handed Over

Click Here to View Gallery

Gurgaon (Ph-II)

13

Mar 98

May 99

Sep 02

852

2.5%

800

40

Handed Over

Click Here to View Gallery

Hyderabad (Ph-I)

6.5

Jan'99

Jan'99

June 01

344

3%

485

19

Handed Over

Click Here to View Gallery

Hyderabad (Ph-II)

3

Aug 01

Jun 03

Feb 06

178

7%

850

18

Handed Over

Click Here to View Gallery

Hyderabad (Ph-III)

6.5

Jan 06

Sep 07

Oct 12

380

41%

1560

82

Handing Over in Progress. 355DUs already handed over

Click Here to View Gallery

Jaipur (Ph-I)

3

Feb 02

Nov 02

Oct 05

184

16%

850

16

Handed Over

-

Jaipur (Ph-II)

6.8

Jan 08

Sep 08

Mar 12

572

20.5%

1964

154

Handing Over in Progress. 521DUs already handed over

Click Here to View Gallery

Kharghar

19

Oct 94

Feb 96

Sep 98

1230

-2.43%

1000

92

Handed Over

-

Kochi

3

Nov' 97

Sep'98

Jun 01

43

5.00%

700

5

Handed Over

-

Kolkata (Ph-I)

10

Nov 92

Nov 95

Oct 97

576

5.00%

510

29

Handed Over

-

Kolkota (PH-II)

10.06

June 10

June11

Nov 2014

582

17%

2673

221.94

Handing Over in Progress.

Lucknow (Ph-I)

4.5

Oct 05

Dec 06

Aug 08

130

8%

1150

20

Handed Over

-

Mohali (PH-I)

9.56

Nov 06

Jul 08

Apr 13

603

23.15%

2266

174

Handing Over in Progress. 316DUs already handed over

Click Here to View Gallery

Meerut (Ph-I)

1.91

Oct 07

Oct 09

Dec 13

90

13%

1724

22

Handing Over in Progress. 60 DUs already handed over

Click Here to View Gallery

Navi Mumbai

6.2

Nov 92

May 94

Jun 96

384

21.30%

706

23

Handed Over

-

Noida (Ph-I)

12

Jan 94

May 95

Sep 97

692

3.00%

550

33

Handed Over

-

Noida (PH-II)

8.25

Jan'97

Jan'97

Sep 98

508

-1.95%

650

29

Handed Over

-

Noida (Ph-III)

16

Nov 99

Aug 00

Dec 03

980

16%

1055

100

Handed Over

-

Noida (Ph-IV)

13

Aug 01

Apr 02

Feb 05

720

9%

1110

85

Handed Over

-

Noida (Ph-V)

11

July 03

Dec 04

Mar07

576

4.2%

1377

100

Handed Over

-

Panchkula (Ph-I)

2

Feb 95

Nov 95

Jan 97

98

6.60%

525

4.5

Handed Over

-

Panchkula (Ph-II)

5

April 02

Jan 04

Jul 06

240

19.6%

1020

22

Handed Over

-

Pune(Ph-I)

5

Apr 00

Aug 00

Jan 03

159

11.5%

685

10

Handed Over

-

Pune (Ph-II)

5.0

Jul 06

Jan 07

Dec 08

148

18%

1535

23

Handed Over

-

 

Note*: Please click project name to know the current status of respective project